Delivery & Customer Plans

Every project needs a plan — but not the bloated, carved-in-stone kind. Bootstrap plans are alive. They breathe, shift, and evolve.

There are two plans you care about: the Delivery Plan and the Customer Plan. One is for you and your team. The other is for the people paying.

Delivery Plan (Living)

  • Built for the delivery stake (Knights (Delivery SMEs), partner Gatekeepers, anyone hands-on).
  • Must have outcomes as milestones. If it’s not tied to an outcome, it’s noise.
  • Format doesn’t matter — kanban board, gantt chart, grid, whatever.
  • Granularity rule: every task must directly affect progress. If it doesn’t move the needle, bin it.
  • Document owners for tasks. If no one owns it, it won’t get done.
    • The Alchemist (PM) should identify one core owner. Multiple owners risks triggering a 'bystander effect' where everyone assumes (or perhaps wishes) that someone else will manage it. A single owner, whether a Knight or Artisan, ensures accountability.
  • Keep it alive. Update as things shift. Don’t let it rot.
  • Make sure to factor in public holidays and resource holidays.

The delivery plan will need to take into account the resource budget, e.g. the customer may have bought 10 days consultancy, but an additional 5 days effort and deliverables are needed from the customer. Your plan will need to take account of the 15 days of effort, but you will need to track 10 days of budget. Unfortunately most PM tools do not account for this, so you may need a seperate budget tracker, unless you have a highly integrated solution that includes timesheets that the Castellan (Account Manager) can trust.

Other options may be to assign the customer 0 costed effort, but X timescale if the software allows for that.

Most software is quite limited in that it doesn't allow for distinctions for public holidays across territories - if you are dealing with a global project, you may be better off knocking something up in Excel using ChatGPT to get you the automation you need.

Customer Plan (Light)

  • Built for the customer stakeholders, especially the Custodian (Customer KDM) with the money.
  • High-level milestones only — no one outside the delivery team cares about sub-tasks.
  • Includes deliverables that the customer Artisans and their 3rd party Gatekeepers must produce.
  • Should fit in an email or slide.
  • Tone = clarity. They need to know what’s coming, when, and what they own.

The Handshake

Delivery Plan = detail.
Customer Plan = story.

Both must line up. If they drift apart, you’re in trouble.

When to Pivot

  • Budget overrun? → Update both plans.
  • Undocumented change? → Only update delivery plan if the change is still in progress. Don't update the customer plan, but document retrospectively.
  • Outcome dropped or swapped? → Update both plans.

Living means living. If the plan doesn’t reflect reality, it’s a liability.

Effort Forecasting

Forecasting is fundamental to bootstrapping. No fluff. You need a number you can stand behind.

Estimating: Fermi First

  • The Alchemist (PM) must be able to Fermi (or have someone who can). Back-of-the-envelope, reasoned, defensible.
  • Step 1 — Classify the task
    • BAU / routine: repeatable, known, stable (e.g. “install standard VM image”). Use the last known good duration. Don’t overthink.
    • Ambiguous: some unknowns. Note them.
  • Step 2 — Reduce ambiguity
    • Compare to last similar work: Was it a new image last time? Any snags? How long did fixes take?
    • Borrow history ruthlessly.
  • Step 3 — Full unknowns
    • Use a Fermi estimate (e.g. “install image in GCP VM — never done before” → break into sub-steps, size each quickly, sum).

Buffer rule: take the Knight’s (SME) effort and multiply by 1.5.
You present the total to the customer. Start high so there’s room to come down (they will try to push it down).

Iron Bootstrap Rule: the project does not proceed unless every task is accounted for and estimated.

When writing estimates, give yourself room to breath. Most customers (particularly budget-conscious customers) are going to try to haggle you down so leave something to haggle. If the Envoy (Sales) is weak they might even go in with the bare minimum effort or cost, leaving you with no breathing room for anything to go wrong. Bootstrap-PM is about acknowledging that most projects will face unforeseen circumstances.

If the Envoy (Sales) has stiffed you, don't be afraid to communicate this to the customer - better to say "I told you so" than "it's not my fault".

How to Write the Estimate (keep it blunt)

Task Type (BAU/Ambig/Unknown) SME Effort (d) Buffer x1.5 Published Effort (d) Notes/Assumptions
Install VM image BAU 1.0 1.5 1.5 Same image/version as last month
New image (vNext) Ambig 1.5 2.25 2.5 Last time driver issue (+0.5d)
GCP VM first-time Unknown 2.0 3.0 3.0 Fermi: net + firewall + perms

Document as estimate. Call out assumptions and traps.

Example

Delivery Plan Milestone

  • Outcome: “Migrate core finance reports”
  • Tasks: Extract dataset / Transform / Load / Validate / Customer sign-off
  • Owner: Dev Lead (Knight) + Finance SME (Artisan)
  • Status: In progress

Customer Plan Milestone

  • “Finance reports available in new system by 31st March”
  • Customer deliverable: Provide dataset by 15th Feb
  • Sign-off: CFO (usually the Custodian (Customer KDM))

Checklist

  • Build Delivery Plan (outcomes as milestones, granular tasks, owners).
  • Build Customer Plan (milestones only, includes their deliverables).
  • Confirm both line up.
  • Share Delivery Plan with delivery stake only.
  • Share Customer Plan with stakeholders.
  • Keep both alive. Update on every major change.

Estimation

  • Task classified (BAU / Ambig / Unknown)
  • History reviewed (last time, snags, fixes)
  • Fermi used where needed
  • Buffer x1.5 applied and published
  • Assumptions + traps written down
  • Every task estimated (iron rule)