Change Management

Changes will happen. Ordinary ones can follow standard protocols. Retroactive ones are the landmines.
The Alchemist (PM) has to handle both with speed, evidence, and leverage.

Ordinary Changes

  • These can follow standard frameworks (e.g. ITIL) — no need to reinvent the wheel.
  • Bootstrap PM’s job is to identify upfront what parts of delivery will require a change and what type.
    • Example: VPN setup, user accounts, firewall rules. Effort might be 0.5 days, but approval could take 5.
  • Build this into the plan — every change must carry both:
    • Effort number (how long to do it)
    • Timescale number (how long it takes to be approved)

Log change requests as soon as possible. Don’t wait until Day 1 to request VPN access — that’s 5 days wasted with the team sitting idle.

  • Use previous projects to anticipate likely changes. Customers often don’t know — lead with assumptions.
    • Example email: “Assuming we’ll need firewall changes for X. If I don’t hear back by EOD, I’ll raise the request.”
    • People will correct bad assumptions faster than they’ll answer open questions.

Change scope types:

  • Simple: (e.g. change button colour). Still document it — scope change matters.
  • Complex: (e.g. switch database tech stack)). Expect commercial discussion with the Custodian (Customer KDM) and Castellan (Account Manager).
  • Removed functionality: customer drops a feature. Must document.
    • Evidence is vital in case of miscommunication or future disputes.
    • Don’t assume freed-up budget can be spent elsewhere. Confirm with customer before reallocating.

Retroactive Changes (Scope Creep)

This is where Knights (SMEs) or well-meaning consultants slip in changes before the Alchemist (PM) even knows.

  • Customers like to “slide things in” and still expect on-time delivery.
    • Knights like to be helpful — and it strokes their reputation.
  • But every one of these must be documented. No exceptions.

Handling Retroactive Changes

  • Small (cosmetic)

    • Example: button colour red → blue.
    • Not worth tracking as effort.
    • Still log as scope change.
  • Medium (functional)

    • Example: send an email on form submit.
    • Has an effort cost, may have design impacts.
    • If project is behind → use as leverage for more budget.
    • If project is ahead → document as goodwill/freebie (but keep in pocket if things sour).
    • Always raise risks with the Custodian (Customer KDM). Offer the option to reverse the change (which costs delivery effort).
  • High (structural/strategic)

    • Example: Wholesale system shift, core design change.
    • If causes you to say out loud, “What the hell are you doing?!” — it’s high.
    • Stop project activity immediately.
    • Call an all-hands with all stakeholders.
    • If customer-led - must trigger payment or penalty.
    • If Knight/delivery-led - that team eats the pain.

Checklist

Ordinary Changes

  • Identify all changes required for setup/delivery.
  • Log change requests early (before project start if possible).
  • Build both effort + timescale into the plan.
  • Use assumptions to provoke correction and speed.
  • Document all drops/removals of functionality.

Retroactive Changes

  • Detect and log every change (no exceptions).
  • Classify: small / medium / high.
  • Document impact and risks.
  • Escalate medium/high to the Custodian (Customer KDM).
  • Reverse option offered if needed.
  • Evidence stored (email, meeting notes, repo log).

Tone

Bootstrap-PM isn’t anti-change — it’s anti-surprise. Every change is leverage, evidence, and protection. If it’s not documented, then it's a hidden landmine waiting for the wrong foot to fall at the wrong time.